Goals
- Team integration: get new team members at Caltech and SCI-Arc integrated into the project and establish teams and linkages to make sure that the project runs smoothly (target 30 Oct 2010)
- Design development: work out a clear, coordinated description of all aspects of the design, including architectural, mechanical, electrical, plumbing, and fire protection systems (due 23 Nov 2010).
- House model/tour: Provide support and input as needed for virtual house tour and physical model (SCI-Arc lead; due 7 Jan 2011)
|
Technical Challenges
- Integration of SCI-Arc and Caltech activities (people, goals, schedule, deliverables)
- Bring new team members from diverse backgrounds and skill levels up to speed quickly
- Baseline designs for some subsystems not yet in place
|